House is wrapped, and almost all the windows are in. HVAC and electrical are complete, and waiting for inspection.
See the photo gallery for site progress as of September 28.
Monday, September 28, 2009
Friday, September 11, 2009
Site Progress: September 11, 2009
Slab has been poured, and much of the framing is done on the lower floor.
See the photo gallery for site progress as of September 11.
See the photo gallery for site progress as of September 11.